“What do you see as being most common mistake that
people make with Linux migrations?“Brunt: They underestimate the amount of
rehearsal that’s required. They know they have to practice, but
they say, ‘In one month, we’ll do the cutover, and the cutover may
take five days.’ So, by the time they’ve planned the project and
get signed off from everybody, they’re only able to do it maybe
once or twice.“The first time you do something, the migration team is going to
run into lots of problems; so in the first round they fix those and
take another crack at it and still find problems, but their time is
up! Underestimating the amount of rehearsal required is the biggest
mistake you can make…”